Keep-Problem-Try

Keep, Problem, Try: a three-column retro where every problem is expected to come with an experiment. A compact format that is built around change.

What it is

Keep, Problem, Try, usually shortened to KPT, is a three-column retro. Keep is what is working and should stay. Problem is what is not working. Try is what the team wants to do about it: an idea, an experiment, a change in approach. The format spread in agile teams, especially in Japan, where it has been widely used for sprint reviews. Its strength is the third column: because Try sits beside Problem on the board, the two are naturally read as a pair, and a Problem with no matching Try is visibly unfinished.

That structure encourages a particular habit. Instead of listing everything wrong and then deciding what to do, the team practises moving from complaint to experiment while the problem is still fresh. Over a few sprints it builds a reflex of asking "what could we try?" before "who is to blame?", and Try cards are small enough to run in a single sprint, which shortens the time between noticing something and testing a fix.

When to use it

KPT is a good default for a sprint-level retro when the team has already had a few retros and wants more action. It works for teams that like to experiment, and for groups where retros have turned into a venting session, because the Try column insists on a constructive turn. It runs in thirty to forty-five minutes and suits remote teams who want a format they can run quickly.

It is weaker for new teams who do not yet know what to try, and for groups that need to talk about feelings, because a Problem card is expected to lead to a Try, and there is no space for a problem that has no solution yet. If the team has a problem that is real but unsolvable at the moment, say so, and write it as a Problem without a Try rather than forcing a weak experiment.

How to run it, step by step

  1. Explain the pairing. Tell the team that each Problem should lead to a Try, and that a Try should be small enough to attempt in one sprint.
  2. Write cards for ten minutes. Everyone adds Keep and Problem cards first, then Try cards. Encourage people to put Try cards near the problems they address.
  3. Reveal and pair. Show the cards and group each Problem with the Try cards that respond to it. Unpaired Problems are worth noticing.
  4. Vote on Tries. Give each person five votes, mostly for Try cards, and a couple for Problems that have no Try yet.
  5. Choose one or two experiments. Pick the top Tries and make each one specific: what will change, for how long and how you will tell it worked.
  6. Review at the next retro. Start the next session by looking at each experiment, then decide whether to keep it, adjust it or drop it.

Common failure mode

Try cards that are really just reversed problems. "Problem: deployments are slow. Try: make deployments faster." Nothing has been proposed; the team has only restated the complaint in the imperative mood. A good Try names a specific change, a size and a time: "Run the integration suite in parallel on three agents for one sprint and compare build times." Ask whether someone could start tomorrow morning from the card alone. If not, it needs another sentence.

The other failure is trying too many things. A board with six Problems tends to produce six Tries, and the team attempts all of them at once and cannot tell which one made a difference. Vote on Tries and pick at most two for the next sprint, with a defined way to tell whether each worked. The rest remain on the board for later, and nothing is lost by waiting.

Example cards

Keep

  • Pairing on every story that touches the billing code
  • Short daily demo of what is done, not a status round

Problem

  • Builds take 22 minutes, so people context-switch while waiting
  • Three stories were blocked on a design decision nobody owned

Try

  • Run the integration suite on three parallel agents for one sprint and compare build times
  • Name a design decision owner at sprint planning for any story with open UI questions

Frequently asked questions

What does KPT stand for?

Keep, Problem, Try. Keep is what works, Problem is what does not, and Try is an experiment the team will run in response.

How is Keep-Problem-Try different from Start-Stop-Continue?

KPT pairs each problem with a proposed experiment. Start-Stop-Continue lists changes directly. KPT is more specific about the problem, and slower to a decision about stopping things.

How many Try items should we pick?

One or two per sprint. More than that and you cannot tell which change made a difference.

What if a Problem has no Try?

Leave it on the board as a visible Problem. Forcing a weak experiment is worse than admitting that you do not yet know what to try.